'In-principle' approval for diversion of 4577.84 ha of forest land in favour of M/s NHPC Ltd for construction of Dibang Multipurpose Project

NHPC Ltd has informed BSE that Ministry of Environment, Forests & Climate Change vide its letter dated April 15, 2015 has accorded in-principle approval for diversion of 4577.84 ha of forest land in favour of M/s NHPC Limited for construction of Dibang Multipurpose Project (3000 MW) on Dibang River in Lower Dibang valley district of Arunachal Pradesh.
17-04-2015
Bigul

Shareholding Pattern For March 31, 2015

NHPC Ltd has informed BSE about the Shareholding Pattern as on March 31, 2015.
14-04-2015
Bigul

Signing of Memorandum of Understanding (MoU) 2015-16 between Ministry of Power and NHPC Ltd.

NHPC Ltd has informed BSE that in compliance with Guidelines issued by Department of Public Enterprises (DPE), NHPC Ltd has signed an Memorandum of Understanding (MOU) dated on March 31, 2015 with Ministry of Power, Government of India for the year 2015-16. The highlights of the signed MoU inter-alia includes generation target under excellent rating as 22000 MU as against last year target of 21800 MU. Target of gross sales of Rs. 5439 Crore and gross...
01-04-2015
Bigul

Cessation of Director

NHPC Ltd has informed BSE that in pursuance of Ministry of Powers' order dated March 11, 2015, Shri J. K. Sharma, Director (Projects) ceased to be director of the Company w.e.f. March 11, 2015.
12-03-2015
Bigul

Outcome of Board Meeting

NHPC Ltd has informed BSE that the Board of Directors of the Company at its meeting held on February 03, 2015 has accorded its approval to the proposal for the award of EPC contract for the development of 50 MW Wind Power Project at Lakmana, Jaisalmer Distt in Rajasthan along with its comprehensive O&M; for 10 years to M/s. INOX Wind Ltd, Noida.
13-02-2015
Bigul

Intimation regarding incorporation of a subsidiary in joint venture with UPNEDA

NHPC Ltd has informed BSE that a subsidiary Company of NHPC Ltd. as a Joint Venture with Uttar Pradesh New and Renewable Energy Development Agency (UPNEDA) has been incorporated in the name of Bundelkhand Saur Urja Limited on February 02, 2015 for implementation of 50MW Grid Connected Solar Power Project in Uttar Pradesh.
05-02-2015
Bigul

Updates

With reference to the earlier letter dated January 09, 2015, NHPC Ltd has now informed BSE that Unit # IV (130 MW) of Parbati-lll Power Station has been synchronized to Grid at 19.33 Hrs. on February 02, 2015. Further, Repair works related to water conducting system and pressure shaft have been completed (Power station was under complete shutdown since November 19, 2014), restoration of other Units are in progress as per schedule.
04-02-2015
Bigul

Announces Q3 results & Limited Review Report for the Quarter ended December 31, 2014

NHPC Ltd has announced the following Unaudited Standalone results for the quarter ended December 31, 2014:The Company has posted a net profit of Rs. 1798.30 million for the quarter ended December 31, 2014 where as the same was at net profit of Rs. 2593.50 million for the quarter ended December 31, 2013. Total Income is Rs. 14675.60 million for the quarter ended December 31, 2014 where as the same was at Rs. 13970.10 million for the quarter ended December 31, 2013....
03-02-2015
Bigul

Closure of Trading Window

With reference to the earlier letter dated Janyary 21, 2015 regarding Q3 results on Feb 03, 2015, NHPC Ltd has now informed BSE that the trading window for dealing in the securities of the Company shall remain closed for all directors / officers / designated employees of the Company from January 27, 2015 to February 04, 2015 (both days inclusive).
22-01-2015
Bigul

Q3 results on Feb 03, 2015

NHPC Ltd has informed BSE that a meeting of the Board of Directors of the Company will be held on February 03, 2015, inter alia, to consider financial results of the Company for the quarter ended December 31, 2014 (Q3).