Approval delays behind halt in work on Australia coal project: Adani
Two contractors were last week told to stop work on the Carmichael mine23-07-2015
Approval delays behind halt in work on Australia coal project: Adani
Two contractors were last week told to stop work on the Carmichael mineAdani Suspends Two Carmichael Contractors: Report
Project manager Parsons Brinckerhoff and Korea's POSCO Engineering & Construction Co Ltd, which is also touted as an investor in the final project, were told late last week to stop work on the Carmich...Adani Says Approval Delays Halt Work on Australia Coal Project
Output from the mine, one of a handful under development in the Galilee Basin of Queensland state, will be mostly exported to India, where it will be central to plans by Indian Prime Minister Narendra...Opposition targets TN govt's MoU with Adani Group
Political parties in Tamil Nadu have raised their voice against Tamil Nadu Government's decision to procure solar-based power from Adani for Rs 7.01 per unit. While the opposition have alleged State's decision to procure power for 25 years will ...Adani Transmission follows port business to offshore bond market
Adani Transmission India is looking to raise around $1 billion through a debut offshore bond offering, according to sources familiar with the matter.Fixes Book Closure for Dividend & AGM (Cut-off date for e-voting)
Adani Enterprises Ltd has informed BSE that the Register of Members & Share Transfer Books of the Company will remain closed from August 04, 2015 to August 11, 2015 (both days inclusive) for the purpose of Payment of Dividend & 23rd Annual General Meeting (AGM) of the Company to be held on August 11, 2015.Further, the Company has fixed August 04, 2015 as the cut-off date for the purpose of e-voting, for ascertaining the names of the Shareholders,...Adani Group to discuss Vizhinjam project with Oommen Chandy
A meeting has been scheduled to work out implementation details of the deep-sea port projectShareholding Pattern For June 30, 2015
Adani Enterprises Ltd has informed BSE about the Shareholding Pattern as on June 30, 2015.Disclosures under Reg. 31(1) and 31(2) of SEBI (SAST) Regulations, 2011
Ventura Power Investments Pvt Ltd has submitted the disclosure under Regulation 31(1) and 31(2) of SEBI (Substantial Acquisition of Shares & Takeovers) Regulations, 2011 to BSEAdani Enterprises Ltd reply to clarification sought by the exchange
The Exchange had sought clarification from Adani Enterprises Ltd with respect to news appearing in Economic Times on June 25, 2015 titled "Adani Stops Work at Aussie Mining Project."Adani Enterprises Ltd response is enclosed.