Bigul

EGM on Feb 07, 2011

Jayaswal Neco Industries Ltd has informed BSE that the Extra Ordinary General Meeting (EGM) of the Company will be held on February 07, 2011.
07-01-2011
Bigul

Expansion Projects Debt tie-up

Jayaswal Neco Industries Ltd has informed BSE regarding "Expansion Projects Debt tie-up"Announcement:"The Company has successfully achieved Debt tie-up of Rs. 1800 Crores for its Integrated Steel Project in Chhattisgarh from ICICI Bank Ltd, Mumbai.The Debt tie-up of Rs. 222 Crores for development of Moitra Coal Block in Jharkhand and additional 1 Lac TPA Coke Oven Plant and its associated 6 MW Power Plant in Chhattisgarh has already been achieved....
31-12-2010
Bigul

Disclosures under Reg. 8A of SEBI (SAST) Regulations, 1997

Jayaswal Neco Industries Ltd has submitted the disclosure under Regulation 8A of SEBI (Substantial Acquisition of Shares & Takeovers) Regulations, 1997 to BSEThe Company has informed BSE about the details of the 30,00,000 Equity shares of the Company pledged by M/s Jayaswal Holdings Pvt Ltd one of the Promoter Group entities of the Company in connection with sanction of Working Capital credit facilities of Rs.350 crores by Punjab National Bank to the Deify Infrastructure Ltd....
13-12-2010
Bigul

Limited Review for the quarter ended Sep 30, 2010

Jayaswal Neco Industries Ltd has informed BSE that the auditor's have conducted the limited review of the unaudited financial results for the quarter ended September 30, 2010.
23-11-2010
Bigul

Financial Results for Sep 30, 2010

Jayaswal Neco Industries Ltd has informed BSE about the Financial Results for the Quarter ended September 30, 2010.
28-10-2010
Bigul

Resumption of Operations of Blast Furnace after the Capital Repairs

With reference to the earlier announcement dated September 16, 2010 about the Planned Shut down of the Blast Furnace for undertaking the Capital Repairs, Jayaswal Neco Industries Ltd has now informed BSE that the job of Capital Repairs has since been completed and the heating of the Blast Furnace and its operations have been resumed from October 13, 2010. The normalcy of production of Hot Metal from the Blast Furnace will now be achieved shortly.
18-10-2010
Bigul

Planned shut down of Blast Furnace of the Company for Capital Repairs

Jayaswal Neco Industries Ltd has informed BSE that the Blast Furnace and other facilities connected therewith under Steel Plant Division of the Company at Raipur shall be shut down for a period of about 25 days commencing from September 18, 2010 for the purpose of undertaking Capital Repairs.The Capital Repairs to the Blast Furnace has been considered necessary to reset the technical parameters of Blast Furnace after which it is expected that Productivity of Furnace will improve....
16-09-2010
Bigul

Fixes Book Closure for AGM

Jayaswal Neco Industries Ltd has informed BSE that the Register of Members & Share Transfer Books of the Company will remain closed from September 27, 2010 to September 30, 2010 (both days inclusive) for the purpose of 37th Annual General Meeting (AGM) of the Company to be held on September 30, 2010.
15-09-2010
Bigul

Financial Results for Jun 30, 2010

Jayaswal Neco Industries Ltd has informed BSE about the Financial Results for the Quarter ended June 30, 2010.
12-08-2010
Bigul

Result of Postal Ballot

Jayaswal Neco Industries Ltd has informed BSE that the members of the Company, by way of Postal Ballot, have passed the following resolutions:-1. Alternation of Sub- Clause 3 of Clause III (B) of Memorandum of Association to provide inter alia supply by the Company of middlings & rejects generated in the process of washing coal to the subsidiary Company "Raigarh Energy Ltd"....