SJVN inks pact with Tata Power Solar Systems for 1,000 MW solar project

State-owned SJVN Ltd on Thursday inked a pact with Tata Power Solar Systems to build a 1,000 MW solar project worth Rs 5,500 crore in Bikaner, Rajasthan. "SJVN today entered into an EPC agreement for 1,000 MW solar project in Bikaner, Rajasthan with M/s Tata Power Solar Systems Ltd," a company statement said. The contract agreement was signed in the presence of Nand Lal Sharma, Chairman and Managing Director of SJVN by Chief General Manager (ECD), SJVN S K Sood, and Vepul Jain, Chief - Business Development, Tata Power Solar Systems Ltd. Sharma said this Rs 5,500 crore-EPC contract is the country's biggest solar contract awarded till date. The contract includes end-to-end delivery of commissioned solar plant to SJVN including arrangement of land on outright purchase basis, power evacuation system up to the ISTS (inter-state transmission system) sub station, and operation and maintenance of the solar PV plant for three years. SJVN had secured this 1,000 MW solar project through CPSU
26-05-2022
Bigul

SJVN Ltd - 533206 - Announcement under Regulation 30 (LODR)-Analyst / Investor Meet - Outcome

In compliance with regulation 30 of Securities and Exchange Board of India (Listing Obligations and Disclosure Requirements) Regulations, 2015, this is to inform you that the audio recording of conference call held with Investors and Analysts to discuss the financial results for the fourth quarter/year ended 31st March, 2022 is available under the corporate announcements head of investor relations section on the website.
26-05-2022
Bigul

SJVN Ltd - 533206 - Corporate Action-Board approves Dividend

In compliance with Regulation 30 and 33 of SEBI (Listing Obligations & Disclosure Requirements) Regulations, 2015 It is informed that the Board has recommended a Final Dividend of ?0.55/- per Share of ?10/- each for the FY 2021-22 subject to the approval of shareholders in the ensuing Annual General Meeting. The Final Dividend is in addition to the Interim Dividend of Rs.1.15/- per Equity Share for the Financial Year 2021-22 paid in the month of February, 2022 and will be paid within the statutory period as per the Companies Act, 2013.
25-05-2022
Bigul

SJVN Ltd - 533206 - Financial Results For The Period Ended 31.03.2022

In compliance with Regulation 30 and 33 of SEBI (Listing Obligations & Disclosure Requirements) Regulations, 2015 Audited Financial Results of the Company (both standalone and consolidated) for the Financial Quarter/Year ended 31st March, 2022 as approved by the Board of Directors are being forwarded herewith for your kind information and record please.
25-05-2022
Bigul

SJVN Ltd - 533206 - Announcement under Regulation 30 (LODR)-Analyst / Investor Meet - Intimation

In Compliance with regulation 30 of Securities and Exchange Board of India (Listing Obligations and Disclosure Requirements), Regulations 2015, we inform you that a Conference Call with Investors and Analysts is scheduled to be held on Wednesday, 25th May, 2022 at 04:30 P.M. 1ST to discuss the Financial Results for the fourth quarter/year ended 31st March, 2022. Further details in this regard are posted on the Company's website under the Investor Relations section.
23-05-2022
Bigul

SJVN Ltd - 533206 - Board Meeting Intimation for Intimation Of Board Meeting To Consider Financial Results For The Quarter And Year Ended 31St March, 2022 And Final Dividend, If Any.

SJVN Ltdhas informed BSE that the meeting of the Board of Directors of the Company is scheduled on 25/05/2022 ,inter alia, to consider and approve Pursuant to Regulation 29 of SEBI (Listing Obligations and Disclosure Requirements) Regulations 2015, this is to inform you that a Meeting of the Board of Directors is scheduled to be held on Wednesday, 25th May, 2022 inter-alia, to consider and approve the Financial Results of the Company for the Quarter and Year ended 31st March, 2022 and recommend the final dividend, if any, for the Financial Year 2021-22. Further for the purpose of above and in terms of Company''s Code of Conduct for Prevention of Insider Trading, the intimation regarding the closure of trading window [i.e. from Friday, 01st April 2022 till 48 hours after the declaration of financial results for the quarter/year ended 31.03.2022] for dealing in the securities of the Company has already been submitted to the Stock Exchanges. Accordingly, the trading window shall remain closed till Friday, 27th May, 2022.
17-05-2022

SJVN to set up hydel 490 MW Arun-4 power project worth Rs 4,900 cr in Nepal

State-owned SJVN Ltd will develop another hydro power project Arun-4 worth Rs 4,900 crore in Nepal. A Memorandum of Understanding (MoU) for the development of the 490 MW Arun-4 hydro electric project in Nepal has been signed in Lumbini, Nepal in the presence of Prime Minister Narendra Modi and Prime Minister of Nepal Sher Bahadur Deuba, the company said in a statement on Monday. SJVN Chairman and Managing Director Nand Lal Sharma said it will be the third mega project to be constructed by the company in Nepal. The construction of 900 MW Arun-3 project is in progress and the 669 MW Lower Arun project is at the survey and investigation stage. With the MoU, signed by Sharma and Nepal Electricity Authority (NEA) Managing Director Kulman Ghising, SJVN has three projects with a total capacity of 2,059 MW in Nepal. According to Sharma, SJVN is targeting to have 5,000 MW projects in Nepal by 2030. The 490 MW, Arun-4 hydro electric project will be developed as a joint venture by SJVN and N
16-05-2022
Bigul

SJVN Ltd - 533206 - Announcement under Regulation 30 (LODR)-Memorandum of Understanding /Agreements

In compliance with regulation 30 of Securities and Exchange Board of India (Listing Obligations and Disclosure Requirements) Regulations, 2015, this is to inform you that a MoU for development of 490 MW Arun-4 project in Nepal has been signed in Lumbini, Nepal today in the august presence of the Honourable Pime Minister of India, Shri Narendra Modi and Honourable Prime Minister of Nepal Shri Sher Bahadur Deuba. The Project will be developed in JV mode by the Company and Nepal Electricity Authority (NEA) with the company having majority share and is expected to generate around 2100 Million Units of energy per annum.This is the 3rd project of the Company on Arun River basin. Two other projects, i.e., 900 MW Arun-3 and 669 MW Lower Arun are already being developed by the Company. With signing of this MoU, the Company will have portfolio of three projects in Nepal having total capacity of 2059 MW.
16-05-2022
Bigul

SJVN Ltd - 533206 - Financial Closure Of Bagodara Solar Power Project (70 MW)

In compliance with regulation 30 of Securities and Exchange Board of India (Listing Obligations and Disclosure Requirements) Regulations, 2015, this is to inform you that the Company has achieved Financial Closure for Bagodara Solar Power Project (BSPP, 70 MW), Gujarat by allocating necessary debt of Rs. 267.30 Crore out of total project cost Rs. 334.12 Crore required for the project from its foreign currency term loan already in place.